An industrial project’s environmental application can fall apart for two reasons, neither of which has to do with filling out the form incorrectly. This article explains how the competent authority is determined in the Bajío region, why the ecological baseline study is the one that most often delays a decision, and what it can cost to discover these issues too late.
The project start date is the one number everyone on the team knows by heart.
It appears in the presentation sent to corporate headquarters, the lease for the facility, the purchase order for equipment already in transit, and the commitment someone made to the client. Everything else—the budget, scope, and staffing—can be adjusted. That date cannot.
The environmental application is, by far, the process that most often puts that date at risk. Not because the process takes too long: the legal timelines in Guanajuato are reasonable. The delays happen for two reasons that arise well before anyone submits a document at the filing counter.
The first is filing with the wrong authority. The second is filing with the right authority but submitting a study that cannot withstand review.
Article 28 of Mexico’s General Law of Ecological Balance and Environmental Protection lists the works and activities that require federal environmental impact authorization. Three of its provisions bring industrial projects in the Bajío region under federal jurisdiction. Each applies independently, so meeting any one of them is enough.
Because of the industry. Section II places the petroleum, petrochemical, chemical, steel, paper, sugar, cement, and electric power industries under federal jurisdiction. Section VII also covers industrial parks where highly hazardous activities are expected to take place. This is not a hypothetical issue along the Salamanca–Irapuato–Celaya corridor: a food or wire-harness plant falls under state jurisdiction; a plant manufacturing resins, solvents, or specialty chemicals does not.
Because of the land. Section VI includes land-use changes in forested areas, jungles, and arid zones. It also triggers an additional process that many project proponents discover too late: the technical justification study for changing land use on forest land. This study is filed with the federal government and is separate from the environmental impact assessment. There are two applications, not one. This requirement comes up more often than expected in developments along the foothills of the Sierra de Lobos and Sierra de Santa Rosa.
Because of the ecosystem and water. Section IX covers projects in wetlands, mangroves, lagoons, rivers, lakes, and estuaries connected to the sea, as well as their federal zones. Section X covers projects in federally protected natural areas. Guanajuato has no coastline, but it does have Yuriria Lagoon, a Ramsar site, and the Lerma River, a body of national waters.
A project may fall under state jurisdiction because of its industry and federal jurisdiction because of the land it plans to clear. Jurisdiction cannot be determined by averaging the factors; each applicable provision must be assessed separately.
When none of the federal provisions applies, the state is responsible for the review. There has also been a recent institutional change.
Since the administrative restructuring in September 2024, the state environmental authority has been the Ministry of Water and the Environment (Secretaría del Agua y Medio Ambiente). The previous name—the Ministry of Environment and Territorial Planning—still appears in the website’s domain and in the form codes, so people in the industry continue to refer to it by its former initials. It is a minor source of confusion, but documents submitted to the agency should use its current name.
Combining water and environmental responsibilities in one agency is more than an organizational detail. In a state where many aquifers are overexploited, having environmental authorization and water resource management under the same ministry changes the sensible order for planning a project. Water availability is no longer something to address after securing a facility; it is a prerequisite worth resolving in parallel.
The process is called Autorización de Impacto Ambiental and is filed using form FCSMAOT-03-01. The documents reviewed are the environmental impact assessment and, when applicable, the environmental risk assessment. The official timelines are clear:
That is 50 business days in total, or just over two months. No serious industrial project schedule should be derailed by that timeline—yet schedules do get derailed, for reasons we’ll cover shortly.
This is the distinction that sets Guanajuato apart from a simplified two-level view of the process. It is also the one most often overlooked in small and midsize projects.
Municipalities with the technical capacity and established regulations to do so—including León, Irapuato, and Celaya—do more than provide an opinion. They have the authority to issue their own decisions and environmental impact authorizations for projects that fall strictly under local jurisdiction. These include certain residential developments, commercial establishments, and low-impact industries that are not reserved for federal or state authorities.
So the first question for any project is not, “Do I need an environmental impact assessment?” The answer is almost always yes. The question is which of the three inboxes to file it with. Filing with the wrong authority does not mean receiving a denial; it means being told weeks later that the application was not under that authority’s jurisdiction. That time cannot be recovered.
Now let’s assume jurisdiction was determined correctly and the application was filed with the right authority. There is still the second issue, which in practice is the one that delays the most project schedules.
Of all the components of an environmental impact assessment, two are consistently less complete than the others: the ecological baseline—the characterization of the site and its area of influence in terms of flora and fauna—and the analysis of cumulative and synergistic impacts.
The pattern is familiar. The project proponent submits a desktop inventory: lists of potential species based on databases and regional literature, without actual seasonal field sampling. The chapter is formally there. Technically, it says nothing about the site.
The reason is biological and straightforward. Wildlife detectability varies by season. A single survey during the dry season will miss migratory species, fail to capture breeding activity, and systematically underestimate the site’s species richness.
An inventory built this way cannot support the impact assessment or the proposed mitigation measures. The reviewer will identify the problem immediately.
The consequence is predictable and costly: a formal request for additional information, a repeat of the fieldwork phase, and a three-to-six-month extension before the final decision is issued. A 50-business-day process becomes a two-quarter process, and the project start date—the number everyone knew by heart—is missed.
That is not the only risk. Inadequate sampling can miss species listed as at risk under Mexico’s official standard. Discovering them late can require rescue and relocation programs that no one budgeted for, with their own timelines and specialized staff.
The analysis of cumulative and synergistic impacts fails for a different but related reason: it is written as if the project existed in a vacuum. In an industrial corridor where pressure on the aquifer, land, and roads results from dozens of concurrent projects, assessing one project in isolation is the same as not assessing it at all.
An automotive parts supplier leases a facility near Irapuato. The property includes about four hectares of vegetation that must be cleared to make room for maneuvering and parking. The automaker has committed to a project start date, and the equipment is in transit.
The application is prepared in March, during the dry season, using a three-day field survey and an ecological inventory based on regional literature. It is submitted to the state authority.
Two things happen, and neither is a denial.
First, the state authority issues a request for additional information about the ecological baseline: without seasonal sampling, the inventory cannot support the impact assessment or the proposed mitigation measures. The fieldwork must be repeated, this time including the rainy season, which will not begin until June.
Second, during the review, the area to be cleared is found to be forest land. The land-use change falls under federal jurisdiction and also requires a separate technical justification study. The state application was not the right one, and the application that should have been filed needs the same ecological survey that was just flagged.
The project was not rejected. It simply started two quarters later, with the facility leased but sitting idle, the equipment in storage, and a difficult explanation to give to corporate headquarters.
What should be done—and what went wrong
The practical conclusion is reassuring: none of this requires extraordinary resources. It requires planning.
Determine jurisdiction before signing. Reviewing the project against Article 28 takes days, not weeks. It should be done with the project details in hand and the property identified. If it is done after the lease is signed, it is no longer an assessment; it is a discovery.
Verify the land’s classification through documentation. If the site includes forest land, there will be two applications. That should be reflected in the initial schedule—not discovered when the reviewer points it out.
Schedule the ecological survey around the biological calendar. This is the most cost-effective shift in approach across the entire process. A well-planned seasonal survey costs a fraction of what it costs to lose a quarter, and it can make the difference between a chapter that supports the application and one that gets flagged. The rainy season arrives when it arrives, regardless of the date promised to corporate headquarters.
Address water in parallel. With water and environmental responsibilities under the same ministry, treating water availability as a later issue no longer makes administrative sense.
Fifty business days is a timeline any industrial project can work with. Two quarters is not. The difference between the two is almost never decided at the filing counter. It is decided months earlier, when someone determines which authority will receive the application and what evidence will support it.
At HF Safety & Environmental Services, we prepare and provide technical follow-up for environmental impact applications in Guanajuato and the Bajío region. Our work includes jurisdictional assessments, ecological baselines based on seasonal sampling, environmental risk assessments, and cumulative impact analyses. If your project has a committed start date, it is worth having this conversation before signing the lease.
Which agency currently reviews state-level environmental impacts in Guanajuato?
The Ministry of Water and the Environment, established through the administrative restructuring in September 2024. The website and forms still use codes based on the previous name, but documents submitted should use the agency’s current name.
How long does state authorization take?
The agency has 10 business days to respond to the initial application and 40 business days to respond to the environmental impact assessment or environmental risk assessment.
How do I know whether my project falls under federal, state, or municipal jurisdiction?
Compare the project with the provisions in Article 28 of the General Law of Ecological Balance and Environmental Protection. Consider the industry, any change in land use on forest land, the ecosystems involved, and any federally protected natural areas. If none of the federal provisions applies, jurisdiction falls to the state unless the project is strictly local and located in a municipality with established regulations, such as León, Irapuato, or Celaya.
Why is the ecological baseline so often flagged for additional information?
It is often based on desktop inventories without seasonal field sampling. Wildlife detectability varies by season, so a single survey during the dry season underestimates the site’s species richness. Repeating the fieldwork can add three to six months to the process.